I have a scheduled job that runs at 10am each day. It just sends a report. I'm noticing over time that the job is executing later and later. Now it is executing at 10.15am. Anyone else noticed this and it there a way of fixing it without having to go back into the scheduled job and reset the time?

4

This is a problem that's popped up and been squashed a few times - it's a little trickier to fix than it seems.

The current conversation about it is on Gitlab but CRM-17671 provides some historical perspective.

Your best short-term solution is probably Xavier's answer on a very similar question.