4

Recently scheduled reminders stopped working on a site.

on investigation of error logs I found that one reminder out of several was incrrectly configured. I deleted the reminder. The next time the scheduled reminder job ran, all went well but a backlog of 3 months of event reminders sent at the same time.

I've found a similar error on another site, and have disabled scheduled reminder task while investigating and deleting the incorrectly configured reminder.

before I turn the scheduled reminder task back on, how can I stop the backlog of old reminders from sending?

1 Answer 1

7

I have made the same mistake myself, more than once - ugh! To avoid emails being sent when a scheduled job needs to catch up on backlog:

  1. Switch from production to staging mode
  2. Manually execute the schedule reminders job - this will result in an activity being recorded on the participant's contact record, but will not send the email (the desired impact)
  3. Switch back to production - the activities recorded on the participant's contact record will prevent schedule reminders being sent for the same events

Hope this helps!

Tamar

1
  • That's marvellous. Thanks Tamar! Now I've found the next badly configured scheduled reminder. This is going to be a fun afternoon. Commented Nov 20, 2018 at 12:05

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.